Solar Israel

 
b_comp_pro.jpg
 
b_corp_pres.jpg

Regulatory Framework

In January 2009, and based on earlier resolutions, the Israeli Government set a target of generating 10% of Israeli energy consumption from renewable sources. This target implies a capacity build-up of approximately 2GW from renewable sources. Indeed, the Israeli government, through the Public Utility Authority (“PUA”) that is the governmental body that regulates the electricity tariffs, started to promote FITs schemes to encourge solar energy power generation.  

FIT for small installations

In July 2008, the PUA issued a FIT for small rooftop Installations of up to 50KWp.  As of January 2010 the FIT is 2.04 NIS (which equals approximately $0.53 at a 3.8 NIS/USD exchange rate)  and once granted it is fixed for 20 years with annual inflation adjustment . Originally, the total budget allocated to this FIT was 50MWp, of which 15MWp were reserved to residential installations of up to 15KWp. 

In December 2009, the cap for the commercial (15KWp-50KWp) rooftop installations was filled . Accordingly the FIT for the commercial rooftops is no longer available. The FIT is still available for residential installations of up to 15KWp. The PUA may issue a new FIT for rooftops during 2010.
 

FIT for medium-size installations

In January 2010, the PUA issued the FIT for projects with capacity greater of 51KWp. The upper capacity of projects under this FIT is limited by the available capacity of the connection point to the grid distribution network. Generally, the maximum capacity of such connection point is 8MVA, but in certain cases the connection can be increased to 12MVA. The FIT is 1.49 NIS (which equals approximately $0.4 at a 3.8 NIS/USD exchange rate)  and once granted it is fixed for 20 years with inflation adjustment. The total budget allocated to this FIT is 300MW over 5 years.  There is a 5% reduction of the FIT each year starting on 2012 until and including 2014 or upon meeting certain caps – 50MW, then 65MW and finally 85MW – whichever condition is met earlier.

FIT for large-scale installations and Thermo-Solar Projects

In December 2009, the PUA issued a draft FIT and related documents for large scale projects, either PV or thermo-solar. The draft FIT is 1.05NIS (which equals approximately $0.27 at a 3.8 NIS/USD exchange rate) for facilities of up to 60MWp and 0.96NIS (which equals approximately $0.25 at a 3.8 NIS/USD exchange rate) for facilities larger than 60MWp. Once granted to a licensee, the FIT is fixed for 20 years with monthly inflation adjustment. The FIT allows up to 2% use of fossil fuels.  The total capacity allocated to this FIT is 500MWp and it will be in effect until this capacity is reached or 4 years from approval of the FIT, whichever is earlier.  


In SolSpear’s opinion the draft FIT for large scale projects is not economical and we expect that the PUA will receive many comments form industry participants to that effect.  The actual publication of this FIT is expected during 2010In the meantime, the only activity in these areas is through government tenders. There are two tenders that are active – one for two 125MWp CSP facilities and the other for 15MW (+ another 15MW at the option of the government) PV project.  These tenders are past the pre-qualification phase.   

The following table summarizes the existing and planned FITs in Israel


Capacity

FIT (in $USD)*

Inflation Adjustment

Total Cap

Future Reduction

Up to 15KWp

0.53

Yes

15MW

4% a year starting on 2011

15KWp-50KWp

The FIT is no longer available

50KWp- Distribution Grid Point Capacity (8MVA in most cases)

0.4

Yes

300MW

5% a year starting on 2012 until 2014 or upon reaching certain cumulative caps

Up to 60MWp

0.27

Yes

500MW

NA

More than 60MWp

0.25

Yes

 

* Assuming a 3.8 NIS/USD exchange rate

 

 

 
pic-solaril-cat.jpg
 

About Us

SolSpear Energy Ltd. (SolSpear) is an independent solar power producer (IPP).
more...

Green Paper

Download SolSpear GreenPaper.
more...